This is an MCQ-based quiz on Construction Planning And Management.
This includes the Number of operations, Output of labor, Output of machinery, Minor works, Major works, and Large projects.
Frequency distribution curves
Economic saving of time results by crashing
If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
Critical path method
Interfering float is the difference between
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased.
Updating may result in
The technique for establishing and maintaining priorities among the various jobs of a project, is commonly known as
A Milestone chart
Frederick w taylor introduced a system of working known as
Final technical authority of a project lies with
Various activities of a project are shown on bar charts by
Which of the following excavators is most suitable for digging under water?
The process of incorporating changes and rescheduling or replanning is called
The main disadvantage of line organisation, is
A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg. If the coefficient of traction for a wheeled tractor on firm earth is 0.5, the rimpull that this tractor can exert without slipping is
10000 kg
12500 kg
22500 kg
5000 kg
Free float for any activity is defined as the difference between
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and latest start time for its successor activity
Consider the following statements: In the critical path method of construction planning, Free Float can be.
1. Greater than Total Float.
2. Greater than Independent Float
3. Equal to Total Float.
4. Less than Independent Float
1 and 4 are correct
2 and 3 are correct
1 and 4 are correct
1 and 2 are correct
The direct cost of a project with respect to normal time is
Zero
Infinite
Maximum
Minimum
Slack time refers to
An event
An activity
Both A & B
None of the above